Grade 10 building construction – Ground Floors Quiz

1. What is the main purpose of a damp-proof membrane (DPM) under a ground floor slab?

To prevent rising damp and moisture from the ground entering the floor
To make the ground floor fire resistant
To increase the structural strength of the slab
To act as a decorative finish beneath tiles
Explanation:

A DPM is a continuous impermeable layer (usually plastic) placed under the slab to stop moisture rising from the ground into the floor and interior of the building.

2. What is the purpose of a hardcore (or crushed stone) layer beneath a ground floor slab?

To serve as the final finishing floor surface
To replace the need for reinforcement mesh in the slab
To keep termites away by chemical action
To provide a stable, well-draining platform and spread loads evenly
Explanation:

Hardcore (crushed stone or similar) creates a stable base, improves drainage under the slab and helps distribute loads so the slab does not settle unevenly.

3. Which of the following describes a suspended ground floor?

A floor that floats on water-filled cavities for insulation
A floor supported above ground level on beams or stumps, leaving space beneath
A floor made directly on the natural ground with no sub-base
A single layer of compacted murram used as the finished floor
Explanation:

A suspended floor is raised above the ground on beams, blocks or piles, creating a ventilated void beneath and avoiding direct contact with potentially wet or poor ground.

4. Why is reinforcement mesh (steel mesh) used in a ground-bearing concrete slab?

To control cracking by holding shrinkage and temperature cracks together
To act as a waterproof membrane for the slab
To reduce the need for a hardcore layer
To make the slab lighter and more flexible
Explanation:

Reinforcement mesh does not prevent all cracks but helps control and hold cracks that form due to shrinkage or temperature changes, maintaining slab integrity.

5. What is a beam-and-block floor system?

A floor made by pouring concrete directly onto compacted murram
Precast concrete beams laid with hollow concrete blocks placed between them to form the floor
A timber floor laid directly on compacted soil
A decorative tile floor fixed onto plywood boards
Explanation:

Beam-and-block floors use precast concrete beams with infill blocks to create a sturdy suspended floor that is quick to construct and commonly used in many climates.

6. Before pouring a ground floor slab on a site with soft, compressible soil, the best action is to:

Lay tiles directly on the soft soil
Use only a thin cement screed with no sub-base
Improve the ground by removing poor soil and replacing with compacted suitable fill or use piled foundations
Pour the slab immediately without preparation
Explanation:

Soft or compressible soil must be improved (excavate and replace, compact fill, or use deep foundations) to prevent excessive settlement and cracking of the slab.

7. What is the role of a sand-cement screed on top of a ground floor slab?

To absorb moisture from inside the building
To act as the primary structural layer carrying loads of the building
To provide a smooth, level bedding for the final floor finish like tiles
To replace the need for a DPM
Explanation:

A sand-cement screed is a thin layer used to level the slab and give a suitable surface for finishes such as tiles or vinyl; it is not the structural slab layer.

8. Which concrete mix is commonly used for ordinary ground floor slabs in many small building works?

1 part cement : 2 parts sand : 4 parts aggregate (1:2:4)
Only sand and water with no cement
5 parts cement : 1 part sand : 1 part aggregate
Pure cement with no aggregate
Explanation:

A 1:2:4 nominal mix is commonly used for ordinary concrete ground slabs, giving adequate strength for general domestic floors when properly mixed and compacted.

9. Why must a DPM overlap and be sealed at joints when placed under a slab?

To hold the reinforcement mesh in place
To make the slab stronger against heavy loads
To maintain continuity so moisture cannot pass through joints
To allow air circulation under the slab
Explanation:

Overlapping and sealing DPM joints ensures a continuous barrier against moisture; gaps would allow water to penetrate up into the floor.

10. What is the primary purpose of edge (perimeter) beams in a suspended ground floor?

To be used as the final floor finish
To act as a decorative feature only
To replace the need for internal columns
To support the outer ends of floor beams and provide an edge to the slab
Explanation:

Perimeter or edge beams take the load from the ends of floor beams, help tie the floor together, and support the edges of the suspended floor construction.

11. What is the correct reason for providing ventilation openings beneath a suspended ground floor?

To let dust and insects into the house
To reduce the need for insulation above the floor
To allow air to circulate and prevent moisture build-up that can rot timber
To keep the underfloor area extremely hot in dry weather
Explanation:

Underfloor ventilation reduces humidity under suspended timber floors, preventing decay and extending the life of timber members.

12. What is the usual minimum curing period for a concrete ground slab to gain adequate strength?

Curing is not necessary for ground slabs
Exactly 1 year before any load is allowed
Only a few minutes once the concrete is poured
About 7 days of proper curing for normal site conditions
Explanation:

Concrete gains strength over time; initial curing for about 7 days (keeping it moist) is commonly recommended to achieve reasonable early strength and reduce cracking.

13. What is the function of a sub-base blinding (thin layer of plain concrete) under a floor slab?

To act as the main structural reinforcement for the slab
To serve as the final floor decorative finish
To provide a clean, level surface to lay the DPM and prevent puncture by sharp stones
To cool the ground under the slab during hot weather
Explanation:

Blinding (a thin plain concrete layer) protects the DPM from damage by sharp stones in the hardcore and gives a level bed for the membrane and slab above.

14. Which flooring finish is best suited for wet areas like kitchens and bathrooms on ground floors?

Untreated timber directly on ground without protection
Ceramic tiles because they are water resistant and easy to clean
A loose gravel surface inside the room
Raw earth finished with no treatment
Explanation:

Tiles are durable, water-resistant and hygienic for wet areas; other options would suffer moisture damage or be impractical indoors.

15. What does the term 'overdigging and filling' mean when preparing ground for a slab?

Filling the slab with water before pouring concrete
Excavating deeper than the slab level and replacing poor soil with compacted suitable fill
Digging the shallowest possible foundation to save time
Leaving unstable soft soil in place and pouring the slab on top
Explanation:

Overdigging and filling removes unsuitable soils and replaces them with well-compacted material, providing a stable base that reduces future settlement problems.

16. Why is termite treatment important before constructing a ground floor with timber elements in Kenya?

To protect timber elements and prevent termite damage that can cause structural failure
Termite treatment is not necessary in Kenya
To make the finished floor look brighter
To make the soil more fertile for planting trees nearby
Explanation:

Termites are common in many parts of Kenya; treating soil and timber prevents costly damage and preserves the structural integrity of timber floors and elements.

17. What is the main reason for compacting the sub-base and hardcore beneath a slab?

To allow roots to grow right under the floor
To make the base softer for the slab to bend
To add moisture back into the soil
To reduce future settlement and ensure even load distribution
Explanation:

Compaction removes voids and increases density of the fill so the slab has a stable support and is less likely to settle unevenly, which would crack the floor.

18. What is a raft (mat) foundation used for in ground floor construction?

To act as temporary formwork for beams
To spread building loads over a wide area where soil bearing capacity is low
To provide a decorative edging around gardens
To replace the need for any concrete in the building
Explanation:

A raft foundation is a large concrete slab that carries the loads of the building over the whole footprint, useful where soils are weak and loads must be distributed.

19. What does a slump test check for when assessing concrete for a ground floor slab?

The amount of DPM needed
The workability (consistency) of fresh concrete
The exact strength after 28 days
The colour uniformity of the concrete
Explanation:

The slump test gives a quick measure of concrete consistency and workability on site; it does not measure final strength directly.

20. Why are control (contraction) joints provided in large ground floor slabs?

To permanently weaken the slab at random points
To direct cracking to predetermined lines so cracks are neat and controlled
To avoid using reinforcement mesh
To allow water to enter the slab
Explanation:

Concrete will crack as it shrinks; control joints create weakened lines so the cracks occur there instead of randomly, making them easier to manage.

21. What is the benefit of placing thermal insulation under a ground floor slab in a home?

It replaces the need for a DPM
It causes moisture to collect under the floor
It reduces heat loss through the floor, making the home more comfortable and energy efficient
It makes the slab heavier and harder to build
Explanation:

Insulating under the slab reduces heat transfer to the ground, improving indoor comfort and reducing energy needed for heating or cooling.

22. Which soil condition would most likely require a suspended floor rather than a ground-bearing slab?

Site is indoors on the top floor of a building
Site is in a flood-prone area or has poor, waterlogged soil
Site has paved roads nearby
Site is perfectly dry with strong rock beneath
Explanation:

Suspended floors raise the structure above ground to avoid dampness and flooding and are used where the ground conditions are unsuitable for a direct ground-bearing slab.

23. What material commonly used in Kenya as a sub-base alternative for small domestic floors is 'murram'?

A decorative tile pattern
A waterproof plastic membrane brand
A type of timber used for joists
A locally available lateritic soil used when properly selected and compacted as a sub-base
Explanation:

Murram is a lateritic material widely used in Kenya as a compactable sub-base when well-graded and compacted; it must be suitable and free of organic material.

24. Where should a damp-proof course (DPC) be placed in relation to the finished ground floor level?

Only on the roof to stop rain from entering
On top of the final floor finish as a decorative strip
At least 150 mm above external ground level and at the level of the floor to prevent rising damp
Buried deep beneath the foundation so it never touches the walls
Explanation:

DPC should be placed in walls at a height above external ground to prevent moisture rising into the walls and link with the floor DPM to maintain a continuous moisture barrier.

25. What is the main purpose of providing falls (slopes) on ground floor surfaces in wet rooms?

To prevent people from walking comfortably
To direct water toward drains to prevent puddles and ensure proper drainage
To make the floor look more interesting
To increase the amount of tile adhesive required
Explanation:

Falls ensure water runs to floor outlets rather than pooling, which is essential in bathrooms, kitchens and service areas to keep floors safe and sanitary.

26. Which of the following is a correct sequence when constructing a typical ground-bearing concrete floor?

Excavate and level site → lay hardcore and compact → place blinding → lay DPM → place reinforcement → cast slab
Cast slab first → dig out soil beneath it afterwards → place decoration
Install roof first and then pour the ground slab
Lay final tiles directly on unprepared soil → pour concrete on top
Explanation:

Proper sequence: prepare and compact sub-base, provide blinding, lay DPM, position reinforcement, then cast the structural slab to ensure durability and prevent moisture problems.